1. The assembly partially (vertical)
- Do a trave per trave
- Suitable for buildings with large floor area
- Need a foundation strong enough, CRAVE Mobil move meet range?
- Arm for crane is not too large so that the weight of the components more freely
- Usually for 3-5 levels
2. The assembly by layer (horizontal)
- Do the floor per floor
- Need to find a tool that can lift the entire building
- Because of the large moment of cranes, heavy component is particularly floor plat
- Tower Crane used CXrane Play
- Required for installation of supporting columns
3. The Lift Slab assembly
- Column continuously cast slabs on top of each other
- Hydraulic lifting equipment
- Need to lock the mounting pegs
4. Jack Block Installation
- The top floor above ground prepared Jack hydraulic components mounted below the vertical support
- With the switch set to use hydraulic Jack and placement support (from the concrete block) of all components was appointed to the top
- After reaching the desired height of the floor, the floor is prepared in the ground next
- And so on
5. Combination Installation
- Use a variety of ways to install
- This is the most prevalent